Here is the method statement for liquid applied bituminous waterproofing.
Roof waterproofing method statement.
This method statement shows how is the proper way of application of liquid applied bituminous waterproofing to blinding or pcc as specified in the specification and approved drawing.
Purpose and scope the purpose of this method statement is to describe the measures and ways of the proper application of waterproofing membrane in our project.
The utilization of liquid waterproofing membrane cementitious materials polyurethane liquid membrane and bituminous.
On completion of waterproofing membrane and before undertaking any further activity it shall be tested by plugging the outlets and flooding 50mm above the highest.
3 0 description and sequence of roof waterproofing.
Roof waterproofing method statement doc free download as word doc doc pdf file pdf text file txt or read online for free.
A completed sample template has been included in appendix 1 and a blank template in appendix 2.
Supply and apply 100mm average foam concrete and slope as per approved shop drawing.
Scribd is the world s largest social reading and publishing site.
Page 1 of 16.
Water and thermal proofing of roof of buildings in service base area service berth area and f s o marine.
Roof installation method statement a basic guide to preparation introduction this guidance note gives practical information about creating a method statement.
Unauthorized entry shall be restricted to the waterproofing areas.
The information and in particular the recommendations relating to the application and end use of sika products are given in good faith.
1 0 foam concrete works.
Typical waterproofing details of foundations above the roof slab shall be followed as per approved shop drawing.
Waterproofing is the formation of an impervious barrier over surfaces of foundations roofs walls and other structural members.
Method statement for roof water proofing in steps with responsibility matrix.
If you wish to use the template in appendix 2 to construct your own documents.
Method statement for the application of the mariseal system the liquid applied polyurethane waterproofing system for use on roofs and terraces exposed to uv and domestic pedestrian traffic.
Work shall be carried out as per the drawing and project specifications.
Application of polymer modified bitumen liquid membrane with cement screed for non insulated roof slab.
Table of contents general information.
Water proofing for roof roof waterproofing.
The function of the impermeable barrier is to prevent water penetrations.